| BEAR CREEK RESERVOIR & WATER TREATMENTPROJECT |
MONTHLY CONSTRUCTION PROGRESS
REPORT
(FOR THE PERIOD FROM 12-22-99 THROUGH
01-25-00)
|
- CONTRACT 1 - RIVER INTAKE
& PUMPING STATION RIVER INTAKE STRUCTURE ACTIVITIES ° Completed backfilling and compaction
of soil around the structure. RAW WATER PUMP STATION ACTIVITIES ° Completed excavation for the Raw
Water Pumping Station. GENERAL CONDITIONS ° Project approximately 31% complete
by schedule and 32% through partial payments. - CONTRACT 2 - RAW WATER
TRANSMISSION MAINS ° Contract has been awarded to John
D. Stevens. - CONTRACT 3 - WATER TREATMENT
PLANT °Clearing & grubbing and erosion
control work are completed at the north half of the project - CONTRACT 4 - FINISHED
WATER TRANSMISSION MAINS ° Not awarded to date. - CONTRACT 5 - EARTH EMBANKMENT
& SPILLWAY ° Clearing & grubbing work and
erosion control work are completed.
|
|
|
mainstreetnews.com ® Copyright 2000 MainStreet Newspapers,
Inc. All rights reserved. |
Home / Job Market / Real
Estate / Automotive
/ Classifieds News from Jackson / News from Madison / News from Banks / Sports Jackson Community / Banks Community / Madison Community Archives / Advertising / Printing / History / Links / Search Site Send a Letter / Subscribe / Place a Classified Ad / Online Rates |